Fall 2024 Crack Seal & Surface Treatment Projects
The City of Avondale Public Works Department, in partnership with Weems Asphalt and VSS International, will be undertaking various Surface Treatment Projects in selected subdivisions and Arterials as part of the FY25 pavement preservation program. This project is scheduled to take place from September 3rd to December 6th.
Bulk trash services will be unaffected; collections will occur early in the morning within the project areas. Please ensure bulk trash is placed out by 5 AM on Monday during your service week.
Expect lane restrictions and closures throughout this period. To minimize disruption, signage will be placed before work begins, and door hangers will be distributed 48 hours prior to any activity. Work hours are from 7:00 AM to 5:30 PM, Monday through Friday. Vehicles left in the work zones risk being towed at the owner's expense.
Please note that the schedule may change due to unforeseen factors such as mechanical issues, weather conditions, or material supply delays. The safety of the public is our highest priority throughout this project.
An overview of the project sequence has been provided below. A more detailed map will be delivered to impacted households approximately 3 days prior to the start of work. For questions or more details, please call Public Works at 623-333-4487.
The project under WEEMS ASPHALT have been completed. The projects under VSS have been partially completed, the crack seal has been completed in the scheduled locations. The treatments have been moved to the Spring of 2025, due to current temperatures. We will update the Project Sequence as soon as we have those projects dates.
Project Sequence
WEEMS ASPHALT
Del Rio Ranch Unit 2, Crack Seal – 9/3 to 9/6 - Completed
Del Rio Ranch Unit 2, Surface Treatment – 9/23 to 9/30 - Completed
Durango Park, Crack Seal – 9/9 to 9/12 - Completed
Durango Park, Surface Treatment – 9/23 to 9/30 - Completed
Los Arbolitos, Crack Seal - 9/13 to 9/20 - Completed
Los Arbolitos, Surface Treatment – 10/1 to10/9 - Completed
Ranchette Estate, Crack Seal – 9/23 to 9/25 - Completed
Ranchette Estate, Surface Treatment – 10/10 to 10/15 - Completed
Coldwater Springs, Crack Seal Parcels 15, 16, 17 – 9/26 to 10/1 - Completed
Coldwater Springs, Crack Seal Parcels 15, 16, 17 – 10/16 to11/19 - Completed
Glenhurst, Crack Seal – 10/2 to 10/4 - Completed
Glenhurst, Surface Treatment – 10/28 to 10/31 - Completed
Irving Pl & Hills Subdivision, Crack Seal – 10/7 to 10/11 - Completed
Irving Pl & Hills Subdivision, Surface Treatment – 11/1 to 11/8 - Completed
Roosevelt Park Unit 1, Crack Seal – 10/14 to 10/17 - Completed
Roosevelt Park Unit 1, Surface Treatment – 10/28 to 10/31 - Completed
Tierra @ Rancho Santa Fe, Crack Seal – 10/18 to 10/23 - Completed
Tierra @ Rancho Santa Fe, Surface Treatment – 11/11 to 11/15 - Completed
Whyman Ave, Crack Seal – 10/24 to 10/24 - Completed
Whyman Ave, Surface Treatment – 11/18 to 11/19 - Completed
VSS INTERNATIONAL
Osborn Rd, 132nd Ave to Dysart, Crack Seal – 9/4 - Completed
Westwind, Crack Seal – 9/5 to 9/12 - Completed
Earll Dr, 107th Ave to 106th Ave, Crack Seal – 9/12 - Completed
Crystal Gardens, Crack Seal – 9/13 to 9/16 - Completed
Garden Trails, Crack Seal – 9/17 - Completed
Rio Vista, Crack Seal – 9/18 to 9/19 - Completed
103rd Ave, Encanto Blvd to McDowell Rd – 9/20 - Completed
El Mirage Rd, Indian School to City Limits – 9/23 - Completed
VSS Micro Surface Treatment Schedule
Osborn Rd, 132 Ave from Indian School Rd to Dysart Rd – Spring 2025
El Mirage Rd, Indian School Rd to North City limits - Spring 2025
Crystal Gardens, Spring 2025
Garden Trails, Spring 2025
103 Ave, McDowell Rd to Encanto Blvd – Spring 2025
Westwind, Spring 2025
Rio Vista, Spring 2025