Fall 2024 Crack Seal & Surface Treatment Projects


The City of Avondale Public Works Department, in partnership with Weems Asphalt and VSS International, will be undertaking various Surface Treatment Projects in selected subdivisions and Arterials as part of the FY25 pavement preservation program. This project is scheduled to take place from September 3rd to December 6th.

Bulk trash services will be unaffected; collections will occur early in the morning within the project areas. Please ensure bulk trash is placed out by 5 AM on Monday during your service week.

Expect lane restrictions and closures throughout this period. To minimize disruption, signage will be placed before work begins, and door hangers will be distributed 48 hours prior to any activity. Work hours are from 7:00 AM to 5:30 PM, Monday through Friday. Vehicles left in the work zones risk being towed at the owner's expense.

Please note that the schedule may change due to unforeseen factors such as mechanical issues, weather conditions, or material supply delays. The safety of the public is our highest priority throughout this project.


Project Sequence

WEEMS ASPHALT

Del Rio Ranch Unit 2, Crack Seal – 9/3 to 9/6

Del Rio Ranch Unit 2, Surface Treatment – 9/23 to 9/30

Durango Park, Crack Seal – 9/9 to 9/12

Durango Park, Surface Treatment – 10/1 to 10/8

Los Arbolitos, Crack Seal - 9/13 to 9/20

Los Arbolitos, Surface Treatment – 10/9 to10/18

Ranchette Estate, Crack Seal – 9/23 to 9/25

Ranchette Estate, Surface Treatment – 10/21 to 10/24

Coldwater Springs, Crack Seal Parcels 15, 16, 17 – 9/26 to 10/1

Coldwater Springs, Crack Seal Parcels 15, 16, 17 – 10/25 to11/5

Glenhurst, Crack Seal – 10/2 to 10/4

Glenhurst, Surface Treatment – 11/6 to 11/11

Irving Pl & Hills Subdivision, Crack Seal – 10/7 to 10/11

Irving Pl & Hills Subdivision, Surface Treatment – 11/12 to 11/19

Roosevelt Park Unit 1, Crack Seal – 10/14 to 10/17

Roosevelt Park Unit 1, Surface Treatment – 11/20 to 11/25

Tierra @ Rancho Santa Fe, Crack Seal – 10/18 to 10/23

Tierra @ Rancho Santa Fe, Surface Treatment – 11/26 to 12/4

Whyman Ave, Crack Seal – 10/24 to 10/24

Whyman Ave, Surface Treatment – 12/5 to 12/6

VSS INTERNATIONAL

Osborn Rd, 132nd Ave to Dysart, Crack Seal – 9/4

Westwind, Crack Seal – 9/5 to 9/12

Earll Dr, 107th Ave to 106th Ave, Crack Seal – 9/12

Crystal Gardens, Crack Seal – 9/13 to 9/16

Garden Trails, Crack Seal – 9/17

Rio Vista, Crack Seal – 9/18 to 9/19

103rd Ave, Encanto Blvd to McDowell Rd – 9/20

El Mirage Rd, Indian School to City Limits – 9/23