FY25 Spring Pavement Program

The City of Avondale Public Works Department, in partnership with Weems Asphalt, VSS International, and MR TANNER will be undertaking various Surface Treatment Projects in selected subdivisions and Arterials as part of the FY25 pavement preservation program. This project is approximately scheduled to take place from April 14th - Jume 30th

Bulk trash services will be unaffected; collections will occur early in the morning within the project areas. Please ensure bulk trash is placed out by 5 AM on Monday during your service week.

Expect lane restrictions and closures throughout this period. To minimize disruption, signage will be placed before work begins, and door hangers will be distributed 48 hours prior to any activity. Work hours are from 7:00 AM to 5:30 PM, Monday through Friday. Vehicles left in the work zones risk being towed at the owner's expense.

Please note that the schedule may change due to unforeseen factors such as mechanical issues, weather conditions, or material supply delays. The safety of the public is our highest priority throughout this project.

An overview of the project sequence has been provided below. A more detailed map will be delivered to impacted households approximately 3 days prior to the start of work. For questions or more details, please call Public Works at 623-333-4487.

The maps below outline the sections that will be addressed in the Spring Pavement Program. Dates for VSS will be added once the contractor provide them.


MR TANNER

  • Crack Seal
    1. Oak Park - March 26th and 27th
    2. Verde Trails - March 26th and 27th
    3. Alamar - March 26th and 27th
    4. Rancho Santa Fe - March 26th and 27th
  • Seal Coating
    1. Oak Park – April 21st - 22nd
    2. Verde Trails – April 23rd – June 1st
    3. Alamar – April 23rd – June 6th
    4. Rancho Santa Fe – June 5th – 6th

VSS

  • Micro Surface
    1. Westwind, Micro Surface - April 14th, 15th, 16th, 17th, and 18th
    2. Crystal Gardens, Mirco Surface - April 16th, 17th, 18th, 21st, 22nd, 23rd, and 24th
    3. Garden Trails, Micro Surface - April 15th, 17th, 18th, 21st, 22nd, 23rd, and 24th
    4. Rio Vista, Micro Surface - April 21st, 22nd, 23rd, and 24th
    5. Osborn Rd, 132nd Ave, Indian School to Dysart Rd, Micro Surface - April 14th, 15th, and 16th
    6. El Mirage Rd, just north of Indian School, Micro Surface - April 14th
    7. 103rd Ave, Encanto Blvd to Mc Dowell Rd, Micro Surface - April 17th,18th, and 21st

Weems Asphalt

  • Mill and Overlay - Central Ave “Western Ave to MC85”
    1. Lower Utilities - May 22nd
    2. Milling – May 27th – 28th
    3. Paving – May 29th
    4. Raise Utilities – June 2nd
    5. Temp Striping – June 3rd
    6. Thermo Striping – June 30th

ViaSun

  • Micro - Hilton Dr, Hilton Wy, Hotel Wy, & 112thDr
    1. Crack Seal – April 2nd – 3rd
    2. Micro Surface – April 28th – 29th
    3. Temp Striping – May 1st