Spring 2024 Crack Seal & Asphalt Repair
As part of the FY24 pavement preservation program, The City of Avondale Public Works Department will be completing minor asphalt repairs and applying a Crack Seal treatment from early March to Mid-May during the work hours of 7am to 4:30pm, Monday - Friday. This process with have minimal traffic delays, and signage will be posted at the locations prior to work. We ask residents and commuters to remain mindful of these signs and adhere to any temporary traffic controls. Vehicles remaining in posted work zones are subject to being towed at the owner’s expense. Efforts will be made to ensure that access to homes and businesses is maintained throughout the project duration.
Maps detailing the project sequence have been included below. Schedules are subject to change due to unforeseen circumstances like mechanical breakdowns, weather conditions, and supplier material delays. Public Safety will always be the top priority in completing work.
Project Sequence
• Dysart Ranch - North of Osborn Rd -East of 132nd Ave. Work dates 3/11/24 -3/14/24
• Las Palmeras West, Work dates 3/15/24 – 322/24
• Rancho Santa Fe - North of Encanto and East of Santa Fe Trails, Work dates 3/25/24 – 4/3/24
• Rancho Santa Fe - South of Encanto, Work dates 4/4/24 – 4/15/24
• Rancho Santa Fe Trail (Collector Rd), Work dates 4/16/24 – 4/19/24
• Palm Gardens, Work dates 4/22/24 – 4/23/24
• Crystal Park Estates, Work dates 4/24/24 – 4/25/24
• Garden Lakes – Unit 3 Lot 1-52 TR A & C and the Estates at Garden Lakes. Work dates 4/26/24 – 4/26/24
• Upland Park, Work dates 4/29/24 – 5/2/24
• Coldwater Springs - Parcel 25 & 20, Work dates 5/3/24 -5/7/24
• Field Crest, Work dates 5/8/24 – 5/13/24